Case Study
Talia Apartments FF&E

Project

Install new fixtures, furniture & equipment for luxury apartment complex common areas and for new model room unit in Marlborough, MA.

Solution

  • Provided final mile warehouse to receive in, store & deliver out materials for installation
  • Provided date & time specific assembly & installation per client directed phasing & floor plans
  • Items assembled & installed included:
    • Artwork & mirrors
    • Game room equipment
    • Office furniture
    • Common area tables, chairs, sofas, lamps & other furnishings
  • Project duration - six weeks from date of first receipt thru final installation. Project was completed on time and within budget.